There could be a battle brewing after grid operator PJM’s proposed rule changes to fast-track large projects to serve data centers. The changes would allow connections to 10 proposed projects per year in 10 months as opposed to the multiyear backlog that currently exists. However, opponents say it favors natural gas fueled resources because it requires 500 megawatts to qualify and the projects must be completed in three years.
Read the full story on Inside Climate News. https://insideclimatenews.org/news/13102025/pjm-pursues-rule-change-to-meet-data-center-surge-critics-fear-gas-suppliers-could-benefit/